Assembly of UWR Connect
The system installation begins with the UWR Connect modules, preferably downstream.
Modules are assembled first in width and then in height according to the basin dimensions. Each layer must be assembled as a complete unit. Before installing UWR Pipe modules, all UWR Covers, UWR Connect Rings, and UWR Pin Locks must be installed in the UWR Connect modules.
Modules are connected using UWR Connect Rings and secured with Pin Lock wedges at both top and bottom. Unused openings must be sealed with UWR Covers.
It is recommended to pre-assemble modules on a clean surface before lowering them into the excavation.
For vertical connections within the system, UWR Connect Ring Repair must be used.
The DN 500 rubber seal must be oriented so both seals face the same direction. The repair ring is pressed through both modules to ensure equal fixation.
Assembly of UWR Pipe
Before installing UWR Pipe modules, the base layer must be properly compacted in accordance with relevant standards.
Sides and bottom of UWR Connect modules must be backfi lled and compacted to create sufficient support before installing UWR Pipe.
Once materials are compacted to the top of the modules and secured with Pin Lock, installation of UWR Pipe can begin.
Pre-assembly of three UWR Pipe modules is recommended.
Ask UWR for advice on practical handling.
Pre-assembled units can be ordered.
General Instructions
Som hovedregel installeres anlægget med ”studsende” fra UWR Pipemodulet i vandets strømningsretning.
After installation, all modules must be secured with Pin Lock wedges to prevent displacement and ensure alignment.
Pinlock ensures that the pipe modules do not shift in relation to each other, thus aligning both horizontally and vertically. The modules must be assembled so that they follow each other precisely.
Use of S-Lock is recommended on all external sides. Pin Lock is mandatory.
Side compaction must reach at least 98% Proctor value.
Approved silicone oil spray or lubricant must be used on seals during installation.
All joints must be clean and free of dirt before assembly and comply with drainage regulations.
For horizontal installation of UWR Cover Pipe, a concrete cone must be installed around the pipe. It is important that the UWR Cover and other insertion pipes are firmly secured. CoverPipe 425 is recommended for inspection pipes.
Care must be taken when handling products due to material strength properties.
Only unpack modules intended for same-day installation, especially in rain or frost.
Installation must comply with the legal requirements for the installation of drainage systems/infiltration basins, including, among other things, legally required training.